Dagenham Green

Multi-network collaboration to overcome major infrastructure constraints

21MVACapacity secured
3,500Multi-utility connections
33kVConnection voltage

At a glance

Client

Peabody

Sector

Mixed-use

Service

Electric and Water

Region

East London

 

Project overview

Dagenham Green is one of East London’s largest regeneration projects, transforming the former Ford Motor Company facility into a vibrant new mixed-use community. Delivered over five phases, the development will provide more than 3,500 homes, extensive public green space, community facilities and a new secondary school.

In detail

 

The challenges

Location and scale of the project posed significant delivery challenges. Initial proposals to deliver the 21MVA required cable routes to cross railway infrastructure near Dagenham Dock Station, introducing technical constraints, third-party approvals and the potential for significant programme delays.

The project also required extensive collaboration between UK Power Networks (UKPN), Last Mile Asset Management and another Independent Distribution Network Operator. Coordinating temporary and permanent network arrangements with multiple stakeholders created an unusual and highly complex delivery environment.

With the point of connection to UKPNs network being at the sites main access point, works needed to be carefully coordinated to minimise disruption to construction traffic whilst maintaining safe working conditions.

 

The solutions

Last Mile facilitated a first of its kind collaboration between multiple network operators. Working with UK Power Networks and Optimal Power Networks a temporary and permanent network arrangement was developed – removing the need for a costly railway crossing.

By reconfiguring existing 33kV infrastructure and establishing a temporary 8MVA supply, Last Mile maintained existing customer supplies, reduced customer costs and enabled power to be delivered to the early phases of the development.

Project highlights

£630,000 saved

6 month+ delay avoided

Energised on time

The outcomes

By challenging conventional approaches and bringing multiple network operators together, Last Mile unlocked vital capacity, avoided significant cost and programme risk, and ensured on-time energisation for a major regeneration project delivering 3,500 new homes.

Scope of works:

  • 21MVA capacity secured from the UKPN 33kV network
  • A new primary substation incorporating 33/11kV transformers and associated infrastructure
  • Significant 33kV off-site reinforcement works and diversionary works
  • An 11kV distribution network
  • More than 3,500 electricity connections and 3,500 water connections across the development
  • NAV adoption of the site’s clean and waste water networks
20240923 145812

View more of our work…

Ntt Hh3

NTT Hemel Hempstead 3 Data Centre

Ironbridge Power Station June 2018 1280x800 Cropped2

Benthall Grange: repowering a landmark for 1,000 new homes

20240918indurent Park Chippenham05 Scaled 1

Indurent Park