Complete package and coordinated approach
Last Mile designed and built the full multi-utility infrastructure, including high-voltage and low-voltage electrical networks, water mains and services, fire hydrants, wash outs, and all ancillary equipment. The team worked closely with Northern Power Grid and Northumbrian Water to coordinate installations, energisation, and water adoption, while also consulting with the local Fire and Rescue Service on safety provisions. Providing a single point of contact, Last Mile ensured smooth coordination across the different utilities, simplifying and streamlining the process for the developer throughout.
Night operations and adaptability
To meet the tight deadlines while minimising disruption to the busy bypass, much of the complex off-site engineering works were completed at night, with Last Mile’s engineers managing the operational complexity of night working. In addition, the project manager held multiple detailed meetings with the local highway authority to negotiate the necessary permits associated with working in a busy bypass.
To avoid any delays caused by mid-construction design changes, Last Mile worked flexibly, re-focusing its work on unaffected areas while redesigns for other sections were submitted and approved. This flexibility prevented significant delays and kept the project progressing.